Cryonorm successfully handed over the LCO2 storage and vaporizer system to ECW Energy & Harvest House.

Cryonorm supplied the system as EPC contractor including initial drying, cool down and commissioning of the system.

LCO2 tank has a volume of 288 m³ and water heated vaporizer is able to provide up to 16,000 kg/hr CO2 @ 6 barg into the local gas grid.

Installation is ready to store and vaporize liquefied bio CO2 replacing fossil CO2 and, as such, helping to reduce our carbon footprint.

We like to thank ECW for their faith in Cryonorm and providing us the opportunity to supply such complete system says Ruben Potters, sales manager at Cryonorm.